About PREA
-
The Pennyrile Regional Energy Agency (PREA) is a municipal interlocal agency created in June 2022 by the cities of Guthrie and Trenton, Kentucky. It was established to expand reliable, affordable natural gas supply across the Pennyrile region of western Kentucky. PREA’s first project is the Pennyrile Energy Corridor, a natural gas pipeline serving portions of Todd, Christian, Trigg, Caldwell, and Lyon counties to support economic growth, create jobs, and improve quality of life for unserved and underserved communities and businesses.
-
No private pipeline company has built sufficient natural gas infrastructure to serve the unserved and underserved areas of the Pennyrile region, nor has any shown interest in constructing a line that would adequately meet the region’s growing needs. Existing supply capacity is limited and already constrains further economic development. PREA was created as a public interlocal agency by the cities of Guthrie and Trenton to plan, finance, and build the necessary pipeline as a regional asset that private markets had not delivered.
-
PREA is a municipal interlocal agency created by the cities of Guthrie and Trenton. Board members are appointed by the Guthrie City Council and the Trenton City Commission. Additionally, each local government that is served by PREA and/or where any easements are sought may also appoint an ex-officio representative to the Board.
-
PREA is a municipal interlocal agency that is subject to Kentucky open meetings and open records statutes. Additionally, PREA is a special purpose governmental entity and therefore subject to the oversight of the Kentucky Department for Local Government, including the filing of annual financial reports and audits.
-
No. PREA is a municipal interlocal agency created by the cities of Guthrie and Trenton. As such, it is not subject to the Kentucky Public Service Commission’s general jurisdiction over rates and services as found by the Franklin Circuit Court (Case No: 25-Ci-00555), and confirmed by state legislation. It is, however, subject to PSC oversight for safety requirements.
-
No, PREA board members serve on a voluntary basis and receive no payment nor any other compensation.
-
No, PREA was not created as a profit-making venture, but as a municipal interlocal agency, though revenues must be sufficient to cover all expenses and capital costs.
-
PREA customers will benefit from all revenue generated by the pipeline as revenues will only be used to cover project costs and help keep gas delivery charges as low as possible.
-
No, PREA does not have the ability to impose taxes. All revenues will come from providing service to its customers.
The Pennyrile Energy Corridor
-
The Pennyrile Energy Corridor is a proposed natural gas pipeline corridor along the I-24 region of western Kentucky, designed to expand access to natural gas and support industrial growth and economic development throughout the region. Limited natural gas capacity currently constrains industrial expansion and prevents the region from competing effectively for new industrial projects. The Pennyrile Energy Corridor would expand access to reliable natural gas supplies, help existing businesses grow, and position the region to attract new industries and create jobs, strengthening the region’s long-term economic growth.
-
Beyond its immediate customers, the pipeline will benefit communities throughout the Pennyrile region by expanding the natural gas capacity needed to attract energy-intensive industries, retain existing employers, and support business expansion. These investments can bring new jobs, increase local payrolls, expand the property tax base supporting schools, infrastructure and basic services, and generate additional business for local suppliers and service providers.
-
No, the project was never intended to serve only one industrial customer, but some existing industries expressed their needs early on in the process. PREA hopes to not only meet their needs, but attract additional industries as customers.
-
No. Data centers were not among the targeted industries when PREA initially developed the pipeline project. Decisions about whether to pursue data center development are made by local communities and industrial development authorities, not PREA. If a community within PREA’s service area chooses to pursue a data center, PREA would work to accommodate any natural gas needs, provided doing so does not impose additional costs or burdens on PREA’s existing or future customers.
-
The proposed route was selected based on engineering feasibility, construction costs, access to existing infrastructure, and the goal of minimizing impacts on landowners and the environment. A key advantage is that much of the approximately 53-mile route follows the Interstate 24 alignment, taking advantage of the existing transportation corridor while reducing the need to establish an entirely new route across private property.
-
PREA has acquired about 90% of the easements for the project. The description below gives the status of easements across the five counties served by PREA as of October 16, 2026.
Todd County has 21 property interests acquired, 0 uncontested properties in progress, and 1 contested property.
Christian County has 53 property interests acquired, 6 uncontested properties in progress, and 7 contested properties.
Trigg County has 21 property interests acquired, 1 uncontested property in progress, and 4 contested properties.
Lyon County has 1 property interests acquired, 0 uncontested properties in progress, and 3 contested properties.
Caldwell County has 4 property interests acquired, 1 uncontested property in progress, and 0 contested properties.
Eminent domain and legal process
-
Yes, the Eminent Domain Act of Kentucky contained in Kentucky Revised Statutes 416.540 thru 416.670 confers upon PREA the right to acquire property rights, including easements, by condemnation.
-
The Trigg Circuit Court specifically found that PREA, pursuant to KRS 416.540 to 416.580 was entitled to the permanent and temporary easements that it sought and that it was entitled to immediate possession of the easements by paying to the landowner the amount the Commissioner’s Report had valued the property at. (Trigg Circuit Court Order Granting Interlocutory Judgement, Pennyrile Regional Energy Agency v. Florence E. Wright Trust, 24-CI-00051).
The Christian Circuit Court further found that PREA’s proposed pipeline project is for a public purpose, that PREA acted in good faith in attempting to acquire rights to the property owner’s property prior to pursuing condemnation, and that PREA, pursuant to the Eminent Domain Act of Kentucky is entitled to the easement that it sought. (Christian Circuit Court Amended Interlocutory Judgement, October 12, 2026, Pennyrile Regional Energy Agency v. William R. Elgin, et al, 24-CI-01096).
The Todd Circuit Court found that it was “necessary that [PREA] acquire the property rights” that it sought through condemnation, that it was entitled to condemn the lands under the Kentucky Eminent Domain Act, and that PREA was entitled to immediate possession of the property upon payment of the Commissioner’s value of the property to the Todd Circuit Court Clerk. (Todd Circuit Court Interlocutory Order and Judgment, April 7, 2025, Pennyrile Regional Energy Agency v. Joe Steven Poindexter, 24-CI-00135).
-
No. Once a Court has deemed the condemnation as appropriate and authorized by law, then the matter of compensation may still be tried before a jury if either party does agree with the compensation awarded by the Commissioner’s Report. However, PREA is entitled to possession of the easement while the compensation phase of the condemnation is litigated.
Compensation and easement terms
-
When easement acquisition for the pipeline began in 2022, PREA inquired of other public utilities in the region who had recently constructed pipelines. Most of those asked did not offer payment for easements. One project in 2019 between Guthrie and Springfield, Tennessee along US41 had paid an average per-foot price of $3.76 for easements based on appraisals of each individual parcel. PREA based its offer of $4.00 per foot on this.
-
The price offered and/or paid is decided by the PREA Board. Their goal was to be fair to all landowners by paying a consistent price to all.
-
The basic easement calls for a 30-foot-wide permanent easement and another 30-foot-wide temporary construction easement.
-
A landowner who believes PREA’s offer of compensation is inadequate is welcomed to present to the PREA representatives any evidence or additional circumstances that need additional consideration. If an agreement cannot be reached, then the matter may be resolved through the condemnation proceedings where both sides may present evidence as to the appropriate compensation. Ultimately, a jury will decide the appropriate amount of compensation.
Farming, construction, and property impacts
-
Yes, common agricultural activities can continue once the pipeline is in place. With the pipeline placed a minimum depth of five feet below the surface, the ground can be cropped or grazed. However, permanent structures cannot be placed within the permanent easement.
-
The value of crops damaged by construction or subsequent maintenance activities will be reimbursed to the landowner by PREA. Fences, drains, roadways and other existing improvements will be replaced in kind. The contractor installing the pipeline will be required to segregate topsoil from other excavated material and replace it at the surface.
-
Observation on past projects is that a pipeline does not substantially impact agricultural use or productivity, and it does significantly increase land value.
Pipeline safety and ongoing operations
-
At the property where it’s reasonable and feasible, some locations may have to be entered following the R.O.W.
-
A Natural gas pipeline is regulated by Pipeline Hazardous Material Safety Administration. (PHMSA). Most is delegated through Kentucky Public Service Commission.
-
D2 Energy, LLC has been contracted by PREA for inspection and maintenance of the pipeline. D2 Energy is a 20-year-old company with personnel who have nearly 300 years of natural gas experience.
Project funding
-
The initial $30 million grant has been used for project planning, right-of-way acquisition, environmental services, engineering, gas system consulting, legal and administrative costs. The amount of additional funding will depend on many factors that include the final size of the line, the pipeline route, and market conditions at the time of construction bidding.